Integrated Part C Timetable 2024–2025 Office of Special Education Programs
Updated November 12, 2024, 9:16 AM Download PDFLeading for Equitable Outcomes
Continuous Activities
- Engage in monthly OSEP TA call.
- Participate in ongoing, meaningful engagement with diverse partners.
- Monitor and provide TA and support to local programs.
- Foster internal and external collaboration.
October
-
October 1, 2024: DMS cycle begins.
-
Prepare policy and procedure revisions drafted for Part C grant application process.
-
Analyze data for SSIP implementation activities.
November
-
November 13, 2024: Submit Dispute Resolution data.
-
Review progress data with partners. Discuss revisions to SSIP and document reasons for changes.
December
-
Finalize SPP/APR and initiate partner, ICC certification, and internal approval processes.
January
February
-
February 3, 2025: Submit SPP/APR. Report APR local program performance to public within 120 days.
-
February 19, 2025: Submit Exiting data.
-
Prepare Part C grant application for publication. Schedule any required public hearings.
March
-
Part C application must be published at least 60 days prior to submission, with an opportunity for public comment of at least 30 days.
April
-
SPP/APR clarification period.
May
-
Submit Part C grant application by OSEP's established due date.
-
Report APR local program performance to public.
June
-
-
APR Determinations issued.
-
July
-
Grant awards issued.
-
July 31, 2025: Submit Child Count, Settings data.
August
-
Analyze Child Outcomes and Family Outcomes data. Prepare Indicators C-3 and C-4.
September
-
Analyze data. Prepare Indicators C-1, C-7, and C-8.